The first thing a harbour project teaches you is calendar humility. Ours planned pile driving for November. The sea decided on January. Two months you don't recover by speeding up — you recover them by re-sequencing: utilities first, pontoons next, the harbour office in parallel.

What the concrete tells you

Quay concrete is not building concrete. It lives in salt, under impact, in permanent humidity. We declined the contractor's first mix — market-compliant, insufficient for thirty years. The extra cost: 2.1% of the structural works package. It is the kind of trade-off a spreadsheet never shows and a site visit imposes.

A harbour is judged by what you cannot see: the anchors, the under-slab utilities, the concrete mix. The rest is paint.

The cadence of decisions

Every Friday, a site meeting. Every month, a report to the vehicle's investors: physical progress, committed spend, variances, decisions ahead. When the dredging line drifted by 8%, investors knew that same month — with the corrective measure and its impact on the cash plan.

Where we stand

To date, physical progress stands at 64%. Berths are 41% pre-reserved, above the file's assumption. Delivery remains set on the revised January schedule. We will keep publishing these notes — because investment, in this house, is narrated while it is being made, not only once it is done.